Before a food factory runs its first batch after the December shutdown, the start-up checklist has to prove five things: the water is safe again, nothing moved in while the plant was empty, every engineering job has been cleared for hygiene, the critical control point equipment still works, and the people coming back are fit to handle food. Treat the restart as a planned event with its own sign-off.
Many South African manufacturers close for two to three weeks over December and January. Water stands in the pipes through the hottest weeks of the year while contractors rebuild equipment. The inkjet coder still thinks it is 2026.
If you ran a festive season hygiene audit for the December rush, the restart is the other half of the same plan. The time to plan it is now, in November, while the engineering list for the shutdown is still being written. If you want an independent set of eyes on the first production week, book a GMP audit with ASC for your first production week in January.
In short
- Plan the restart before the shutdown starts. Every engineering job on the list needs a named person who will sign its hygiene clearance.
- Flush every water outlet and check the water before cleaning starts, because cleaning with stale water spreads the problem.
- Swab more after engineering work, and decide before the shutdown whether high risk product is held until pathogen results are back.
- Re-verify every CCP device on the start-up shift, and check that date coders have rolled over to 2027.
- Audit in the first production week, under real line pressure, rather than on the quiet day before it.
Why the first week of January carries the most risk
A running factory corrects itself every shift, because somebody notices the blocked drain or the droppings. Switch the plant off for three weeks and those small daily corrections stop, while the conditions that need correcting carry on.
Stagnant water is the clearest example. Pipework and tanks that sit warm and still over December lose their chlorine residual and give biofilm, and organisms such as Legionella, time to grow. Our article on Legionella in supermarkets explains why every system that sprays or mists water needs flushing after a shutdown. In a factory the same applies to hand basins, hose points, CIP supply lines and any dead leg nobody uses in January.
Engineering work is the second risk. The shutdown is when the big jobs get done, such as a new filler or welding on a platform over an open line. Each one brings swarf and broken glass into an area that was clean on 18 December. Pests are the third. Rodents and cockroaches move into quiet buildings quickly, and birds nest in loading bays that nobody walks through.
Then there are people. Some staff return from the festive season with gastroenteritis. A short return to work health declaration on day one helps catch it, provided nobody is penalised for declaring, and our guide to sick food handlers covers exclusion and the return to work.
What to settle before the gates close
These are the decisions we would put in writing and sign off at management level before the shutdown.
- Run down short shelf life raw materials and finished stock, and quarantine anything open that will not be used before the restart.
- List every engineering and building job with the area it touches and the person who will sign its hygiene clearance.
- Keep the pest control contract running through the shutdown, with at least one inspection in the closed period.
- Decide who answers the cold store and freezer alarms on each day of the shutdown, and test that the alarm actually reaches them.
- Leave the site secure, with access limited to named contractors, because a quiet site is also a food defence weak point.
BRCGS Food Safety Issue 9 already expects a documented hygiene clearance after maintenance work (section 4.7), and the ISO 22002-100:2025 prerequisite requirements, read with the sector part such as ISO 22002-1:2025 for food manufacturing, treat maintenance and pest control as standing programmes. What changes in December is the volume of work squeezed into a short window, which is when clearances get skipped.
Keep contractors from leaving a foreign body behind
Contractors do not think about food safety unless you make them. Brief them at the gate, issue a permit for each job, and require them to account for tools and parts at the end of every day. A missing 10 mm socket on Christmas Eve is easy to find. On 4 January it is a foreign body complaint waiting to happen.
Ask for a glass and hard plastic check of every area where work took place, against your register. If anything broke, follow the procedure in our glass breakage guide before the area is cleaned.
Where the work changed a process step or a product flow, it also triggers a review of the hazard analysis, and a rebuilt oven or fryer needs its first batches checked against the product specification. Confirm that contractors used only food grade lubricants on product contact equipment. Our guide to HACCP review triggers sets out when that review is required and who signs it.
The start-up checklist, area by area
Run it in this order. There is no point cleaning with stale water, or swabbing before the clean is finished.
| Area | Check before the first batch, and the record to keep |
|---|---|
| Water | Flush every outlet, including little used hose points, until the water runs at its normal temperature. Check free chlorine at the furthest outlet. Keep the flushing log and readings. |
| Drains and traps | Refill dry traps and confirm drains flow the right way after floor work. Pre-start inspection sheet. |
| Pest control | Walk the site with the contractor before cleaning, including stored flour and dry ingredients. Contractor report. |
| Engineering work | Signed hygiene clearance for every job. Count tools and parts, then check glass and hard plastic against the register. |
| Cleaning | Deep clean, then a pre-operational inspection of every line. Cleaning records and pre-op sign-off. |
| Swabs | ATP or visual checks on contact surfaces, environmental swabs with extra points where work took place. Swab plan and results. |
| CCP and monitoring kit | Metal detector or X-ray with all test pieces. Thermometers and checkweighers verified and signed on the start-up shift. |
| Cold stores and stock | Read the logger for the whole shutdown, not only today. Check raw materials and packaging for dates and damage. |
| Date coders and labels | Every coder shows the right date and year, and best before dates still use the right shelf life. First-off sign-off per line. |
| People | Return to work health declaration, clean protective clothing and a restart briefing for every shift. |
A freezer that sits at the right temperature on 4 January tells you nothing about Boxing Day. If the logger shows a long excursion, the stock is on hold until someone with the authority to decide has looked at the data. Power cuts and summer storms over the holidays make this likely.
Why the swab plan needs to change for the restart
Construction dust, wet floors and condensation disturb or create harbourage sites. For a ready to eat or high care operation, the start-up is when Listeria monocytogenes is most likely to move from a niche in the building to a food contact surface.
Add swab points around every area that was worked on. Swab after the clean to confirm sanitation, and again a few hours into the first production shifts, when organisms working out of niches show up. In a dry, low water activity plant the target changes to Salmonella and Enterobacteriaceae, and our guide to monitoring dry food plants explains why water is the enemy there.
Pathogen results take days, not hours. Decide in advance whether the first batches of high risk product are held until the environmental results are known. If the answer is yes, plan the warehouse space and the customer orders around it now. Our Practical Pathogen Environmental Monitoring and Surface Swabbing course shows a team how to set those points and what to do with a positive.
How a Gqeberha snack factory would plan its restart
Take a snack and biscuit manufacturer in Gqeberha that stops production on Friday 18 December 2026 and restarts on Monday 4 January 2027. During the shutdown a contractor replaces a section of conveyor on the packing line and a builder repairs a section of floor in the dry store. Before the floor repair, raw materials and packaging in the dry store are covered or moved. This is how we would plan the restart.
| Day | What happens, and who does it |
|---|---|
| Before 18 December | Engineering list signed off with a hygiene clearance owner for each job. Pest visit booked for the closed period. Cold store alarm contacts tested. Led by the production and QA managers. |
| Saturday 2 January | Water flushed and logged, chlorine checked at the furthest point. Pest walk. Drains and traps checked. Conveyor and floor jobs inspected and their hygiene clearances signed. Hygiene team with the pest contractor. |
| Sunday 3 January | Dry clean wherever the line is dry, and the repaired floor fully dried before production. Pre-operational inspection. Enterobacteriaceae swabs, with Salmonella points around the repair and the new conveyor. CCP equipment verified. Hygiene team and QA. |
| Monday 4 January | Health declarations and restart briefing. Coders checked for the 2027 date. First-off checks on every line before packing starts. Production manager and QA sign the start-up release. |
| First production week | An independent GMP audit while the lines are running, with findings fed into the first management meeting of the year. |
Audit the first production week, not the empty factory
An audit run on the quiet day before start-up measures housekeeping. The disciplines that matter, such as whether hands are washed at a changeover or whether the sanitiser is still at strength late in the shift, only show under production pressure. That is why we suggest booking an independent GMP audit for the first full week of production.
An ASC GMP audit is generally one day on site, with a written report about a week later. It is carried out in line with ISO 19011 against R638, the Codex General Principles of Food Hygiene, the ISO 22002 prerequisite requirements and any customer standard you hold, so every finding is traced to a requirement and ranked by risk.
ASC is not a certification body, and the report is written so that a certification body auditor could read it cold and follow it.
Why food businesses choose ASC
Rated 4.9 out of 5 from more than 400 Google reviews across our three offices.
Gqeberha Google reviews Johannesburg Google reviews Cape Town Google reviews
Our online courses hold a 4.9 average from 2,647 course reviews and more than 7,200 course enrolments.
- ISO 9001 certified
- SAATCA registered online training course provider (TC 065)
- FoodBev SETA Accredited Provider No. 587/00337/1900
- Exemplar Global Recognised Training Provider
Book now for your restart week
A GMP audit in your first production week
One day on site while your lines run, a written report about a week later, and findings traced to R638, Codex and the ISO 22002 prerequisite requirements. Led by a registered lead auditor with Exemplar Global and IRCA. One day of audit time costs far less than a week of held stock or a failed retailer visit in January. Auditing is charged hourly. Free, no obligation quote.
Request a GMP audit quote WhatsApp us to book a January date
Training the team that takes the restart swabs? Practical Pathogen Environmental Monitoring and Surface Swabbing (R1,750, nine hours online with lifetime access).
Questions we are often asked
How long before production should start-up checks begin?
For most factories, one to two days. Flushing, the pest walk and the deep clean take a full day on a medium sized site. Swabbing and equipment checks take most of the next.
Do we need to test water after the shutdown?
At minimum, flush every outlet and check free chlorine at the furthest point. Whether you also send samples to a laboratory depends on your water risk assessment and any supply problems over the holidays. If the supply was interrupted, our guide to unsafe municipal water sets out what to do.
Does the December shutdown trigger a HACCP review?
Not by itself. A review is triggered when the shutdown work changes something the HACCP plan relies on, such as new equipment, a changed process step or a different product flow. The team should check the engineering list against the plan before start-up.
Sources
- Codex Alimentarius, General Principles of Food Hygiene, CXC 1-1969, revised 2022. CXC 1-1969 on the FAO website
- ISO 22002-100:2025, Prerequisite programmes on food safety, Part 100: Requirements for the food, feed and packaging supply chain, and ISO 22002-1:2025, Part 1: Food manufacturing. International Organization for Standardization.
- BRCGS Global Standard for Food Safety, Issue 9, section 4.7 Maintenance, including hygiene clearance after maintenance work.
- ISO 19011:2026, Guidelines for auditing management systems. International Organization for Standardization.
- Regulation R638 of 22 June 2018, Regulations governing general hygiene requirements for food premises, the transport of food and related matters, Government Gazette 41730.