Section 37(2) agreements for the December shutdown

When a contractor breaks the Occupational Health and Safety Act on your site, the law presumes that you, the employer who brought them in, broke it too. Section 37(2) applies that presumption to contractors unless you and the contractor have agreed in writing on the arrangements and procedures that will keep the contractor compliant. Without that agreement you are left to prove the narrow section 37(1) defences after the fact.

For a South African food factory, the December shutdown is when this bites. Refrigeration technicians and builders arrive in the same fortnight as the fumigators and electricians, often with their own subcontractors, while your safety officer and half the production team are on leave.

Below is what section 37(2) requires and what ISO 45001 adds, so that the shutdown work does not turn into a January audit finding. If your team needs to build the system properly, our ISO 45001 Understanding and Implementation course includes a full lesson on contractors and the section 37(2) agreement.

In short

  • Under section 37(1) of the OHS Act, an employer is presumed to have committed an offence committed by an employee. Section 37(2) applies the same presumption to a mandatary, which includes a contractor or subcontractor.
  • The presumption falls away only where the parties have agreed in writing to the arrangements and procedures that ensure the contractor complies with the Act.
  • A signed agreement is necessary but not sufficient. Section 9 still requires you, as far as is reasonably practicable, to ensure that people who are not your employees are not exposed to hazards from your activities, so the agreement has to be enforced on site.
  • ISO 45001 clause 8.1.4.2 asks for a process, coordinated with procurement, to select contractors and control the risks running in both directions between your work and theirs.
  • In a food factory every contractor job is also a food safety risk. Production must not restart until the area has had a documented hygiene clearance.

What does section 37(2) of the OHS Act say?

Section 37 of the Occupational Health and Safety Act 85 of 1993 deals with acts and omissions by employees and mandataries. Section 37(1) says that when an employee does something that would be an offence if the employer did it, the employer is presumed to have done it. The employer can rebut that only by proving all three of the following: the employee acted without the employer’s connivance or permission, the act was outside the employee’s authority, and the employer took all reasonable steps to prevent it. Issuing an instruction forbidding the act is not, on its own, enough.

Section 37(2) applies the same presumption to a mandatary of the employer, “except if the parties have agreed in writing to the arrangements and procedures between them to ensure compliance by the mandatary with the provisions of this Act.” The Act defines a mandatary as including an agent, a contractor or a subcontractor for work, without taking away the contractor’s own status as an employer in its own right.

In plain terms, the contractor remains responsible for its own people. The written agreement is what stops their failures from becoming yours. Filed and forgotten, it protects nobody. It has to set out real arrangements, and you have to be able to show they were followed.

What should a section 37(2) agreement contain?

The Act does not prescribe a template, which is why so many agreements are a single page that says the contractor will comply with the Act. That restates the law and arranges nothing. An agreement that will stand up after an incident is specific to the job and the site, and it covers at least the following.

  • The work and where and when it will be done, with the named person in charge for each party.
  • The contractor’s own risk assessment for the job, which you accept before work starts, and how it fits with your hazard identification and risk assessment.
  • Which of your site rules apply, including permits to work, isolation and lockout, hot work, work at height, confined spaces and the hygiene rules of the production areas.
  • Proof of the contractor’s competence and of its registration with the Compensation Fund, or with a licensed compensation insurer, ideally a current letter of good standing.
  • How incidents and near misses are reported, and who investigates.
  • Whether subcontracting is allowed, and the rule that any subcontractor signs the same arrangements before setting foot on site.

Sign it before the contractor arrives, keep a copy at the gate, and brief the people who will supervise the work on what it says. An agreement nobody on site has read is the first thing an inspector will notice.

What does ISO 45001 add for contractors?

If your factory is certified to ISO 45001, or working towards it, clause 8.1.4.2 of ISO 45001:2018 asks for more than a signature. It requires a process, coordinated with your procurement, to identify hazards and to assess and control the risks arising from three directions: the contractor’s work affecting your organisation and its workers, your operations affecting the contractor’s workers, and the contractor’s work affecting anyone else in the workplace. You must also define criteria for selecting contractors on health and safety grounds and make sure your management system requirements are met by them.

In practice an auditor will pick one contractor job from the shutdown and follow it through from the selection record and the agreement to the induction, the permits and the final sign off. A gap anywhere in that chain is a nonconformity. Our ISO 45001 Understanding and Implementation course walks through that chain lesson by lesson, from selection criteria to the section 37(2) agreement. Our guide to running ISO 9001, 14001 and 45001 on the same records shows how one contractor file can serve all three standards.

ISO 45001 is being revised. The draft international standard was published in June 2026 and the new edition is expected in 2027, with more weight on what the draft calls external providers across the supply chain. Until it is published, ISO 45001:2018 with its 2024 amendment remains the standard you are certified against, and a transition period, expected to be three years, will follow publication. Expect to update your procedure when the final wording is out, but a contractor process that works today gives you the evidence base.

Why a contractor job is also a food safety risk

A safety officer looks at a welder and sees burns and fumes. A food safety manager looks at the same welder and sees metal spatter, grinding dust, an open hatch on a mixer and a toolbox that came in with twelve tools and may leave with eleven. Both are right, and the shutdown plan has to cover both.

The GFSI recognised manufacturing schemes, including FSSC 22000, BRCGS and IFS, expect contractors to follow the same hygiene rules as your staff in production areas.

They also expect equipment that has been worked on to be cleaned and formally released before it touches product again. That release is the hygiene clearance: a signed check that the area is free of tools, swarf, packaging, glass and lubricant, that temporary repairs are recorded, and that cleaning has been done and verified. Our post on restarting after the December shutdown sets out the full restart sequence, and our glass breakage procedure covers what to do when a contractor breaks a light fitting over a line.

A worked example: a Johannesburg dairy’s shutdown plan

A dairy in the south of Johannesburg closes from 20 December to 4 January. Four contractor jobs are planned: an ammonia plant service, a new floor in the filling hall, fumigation of the dry goods store, and electrical work on the pasteuriser control panel. The safety officer is on leave from 23 December. The production manager, who will be on site, builds one table for the whole shutdown and has every contractor sign its row before the gate opens.

JobRisksAgreement and permit must cover
Ammonia plant serviceSafety: ammonia release under pressure. Food safety: refrigerant or oil near product areas.Competent person, lockout and the emergency plan, with gas detection
Filling hall floorSafety: dust, chemicals, manual handling. Food safety: dust and resin residues in a high care area.Screening off the area, ventilation, removal of all materials, hygiene clearance before restart
Dry store fumigationSafety: toxic gas exposure. Food safety: fumigant residues on packaging and ingredients.A registered pest control operator, re-entry time and a gas clearance certificate, with stock removed or protected
Pasteuriser panelSafety: electrical shock, unexpected start up. Food safety: changes to temperature control and recording.Electrical lockout, then a calibration check of the probes and recorder, a flow diversion valve test and a holding time check before the first batch is released
One row per job, signed by both parties before work starts.

What makes this plan defensible is ownership and release. The person in charge on site for each day is named, so the 37(2) arrangements still have an owner after 23 December, and each row carries a food safety control as well as a safety control.

The final column ties every job to a release step, so nothing goes back into production on the say so of the contractor alone. If the ammonia plant is large enough to be a major hazard installation, our ammonia refrigeration guide explains the extra duties.

For a dairy, the pasteuriser row deserves particular care. Any change to the controls or the recorder means the critical control point has to be verified before the first batch after the shutdown is released. That is an internal audit question as much as an engineering one, and an internal food safety audit scoped to the shutdown work, quoted on scope, gives you a second pair of eyes.

The new floor is construction work under the Construction Regulations, 2014, so the dairy also has duties as the client. Regulation 5(1) requires it to prepare a baseline risk assessment and a site specific health and safety specification, to appoint the principal contractor in writing, and to make sure the principal contractor is registered and in good standing with the Compensation Fund or a licensed compensation insurer before work starts.

A short checklist for the next four weeks

Most of this can be done now, before anyone goes on leave.

  1. List every contractor job planned for the shutdown, including the ones the engineering team books directly.
  2. Send each contractor your site rules and agreement now, and ask for their risk assessment and letter of good standing from the Compensation Fund or their licensed insurer in return.
  3. Review each risk assessment for food safety hazards as well as safety hazards, and add the controls to the permit.
  4. Name the person in charge on site for every day of the shutdown.
  5. Prepare the hygiene clearance forms for every area that will be worked on, so they are signed before production restarts.

Why food businesses choose ASC

Rated 4.9 out of 5 from more than 400 Google reviews across our three offices.

Gqeberha Google reviews Johannesburg Google reviews Cape Town Google reviews

Our online courses hold a 4.9 average from more than 2,500 course reviews and more than 7,100 course enrolments.

ISO 9001 certified. SAATCA registered online training course provider (TC 065). FoodBev SETA Accredited Provider No. 587/00337/1900. Exemplar Global Recognised Training Provider.

Build the system properly

ISO 45001:2018 Understanding and Implementation, online

About 20 hours, online and self paced, taught on the South African OHS Act, with a lesson on contractors under clause 8.1.4.2 and the section 37(2) agreement. Built for the SHEQ manager or safety officer who has to build or rebuild the system, and the natural step before the internal auditor course. R3,950 per person, and at about 20 hours it can be finished before the shutdown starts. Training several people? WhatsApp us for a team quote.

Enrol on the course WhatsApp us to enrol or get a team quote

Auditing your contractor controls after the shutdown? ISO 45001:2018 Internal Auditor course (R3,850 on special, normally R4,670).

Writing the maintenance risk assessment yourself? Equipment Suitability and Maintenance Risk Assessment Template (RA10) (R690).

Questions we are often asked

What is a section 37(2) agreement?

It is a written agreement between an employer and a mandatary, such as a contractor or subcontractor, setting out the arrangements and procedures that will ensure the contractor complies with the Occupational Health and Safety Act. Without it, the employer is presumed to have committed the contractor’s offence, unless it can prove all three section 37(1) defences.

Does a section 37(2) agreement transfer all liability to the contractor?

No. It lifts the presumption that you committed the contractor’s offence, but your own duties under sections 8 and 9 of the Act remain. You still have to provide a safe workplace and protect people who are not your employees, so the arrangements in the agreement must be enforced on site.

Does every contractor need a section 37(2) agreement?

The Act does not list exceptions by job size. Any contractor doing work for you on your premises is a mandatary, so the safe practice is to have a written agreement for every contractor, scaled to the risk of the job.

Is ISO 45001 changing?

Yes. The draft of the next edition was published in June 2026 and publication is expected in 2027. Until then ISO 45001:2018 with Amendment 1 of 2024 applies, and a transition period is expected after publication. Our ISO 45001 implementation course teaches the current standard.

Sources

  1. Construction Regulations, 2014, GNR 84 of 7 February 2014, regulation 5
  2. Occupational Health and Safety Act 85 of 1993, sections 1 (definition of mandatary), 8, 9 and 37
  3. ISO 45001:2018, Occupational health and safety management systems, Requirements with guidance for use, clause 8.1.4.2, and Amendment 1:2024

Leave a Comment

I accept the Terms and Conditions and the Privacy Policy

Exemplar Global Recognised Training Provider (RTP) badge issued to ASC Food Safety
International recognitionExemplar Global Recognised Training Provider (RTP)Exemplar Global, the international organisation that certifies auditors and recognises training providers, recognises 28 of our auditor, HACCP, GMP and ISO courses, including four lead auditor courses, whether we deliver them in class, in live virtual classes or online.
News & updates 5 new
4.9/5 what do you need today?